AEP's Kentucky Power seeks approval for 760-MW gas plant to serve TeraWulf data campus
- Kentucky Power sought Kentucky regulatory clearance for a new 760-MW combined-cycle natural gas plant at Big Sandy in Louisa.
- A proposed EastPark substation would support TeraWulf's Muskie Data Campus, targeting up to 1 GW of phased demand by 2029.
- Customer benefits include over $500 million in fixed-cost offsets and $100 million in residential winter credits over 10 years from 2029.
- TeraWulf would pay estimated financing costs for plant construction, alongside applicable service charges.
- Regulatory decisions on the proposed generation and transmission infrastructure could come as early as mid-2027.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. AEP - American Electric Power Company Inc. published the original content used to generate this news brief via PR Newswire (Ref. ID: CL97400) on November 13, 2026, and is solely responsible for the information contained therein.