Fortuna Mining advances Diamba Sud gold project permitting in Senegal
- Fortuna Mining received a notice of admissibility for its Diamba Sud exploitation permit application in Senegal on November 2, 2026.
- Final permit approval is expected in the fourth quarter, with a final investment decision to follow.
- Early works are underway; full-scale construction remains subject to the permit, board investment approval and local construction approvals.
- First gold remains targeted for mid-2028, with process plant commissioning and ramp-up scheduled for the second and third quarters.
- Diamba Sud and Séguéla’s 30% plant expansion underpin targeted annual gold production growth of approximately 60% to 500,000 ounces from mid-2028.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Fortuna Mining Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202611021645OMX_____CNEWS_EN_GNW9868554_en) on November 02, 2026, and is solely responsible for the information contained therein.