- US Nuclear Regulatory Commission:

  • SAYS IT BEGUN A SPECIAL INSPECTION AT THE DRESDEN NUCLEAR POWER STATION IN MORRIS, ILLINOIS OPERATED BY CONSTELLATION ENERGY

  • SAYS INSPECTING THE STATION AFTER PLANT STAFF FOUND A CORRODED BATTERY CONNECTION THAT BROKE DURING MAINTENANCE

  • SAYS THE BATTERY IS PART OF A BACKUP POWER SYSTEM THAT SUPPORTS EQUIPMENT USED TO SAFELY SHUT DOWN THE REACTOR

  • SAYS IT DETERMINED A SPECIAL INSPECTION WAS WARRANTED BECAUSE THE DAMAGE WAS NOT CAUGHT DURING ROUTINE CHECKS, AND SIMILAR BATTERY PROBLEMS HAVE OCCURRED AT OTHER NUCLEAR PLANTS

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk