Tribunal bars Gazprom from enforcing Russian court judgment against Linde

By Public Technologies
  • An SCC tribunal on October 15, 2026, barred Gazprom from enforcing a Russian court judgment against Linde over the Amur GPP project.
  • The tribunal ruled that Gazprom's claims must proceed through arbitration under contractual dispute resolution provisions.
  • A Russian court had ruled against the company over damages and lost profits stemming from fires at the facility.
  • Contingent liabilities for this dispute and other Amur GPP contract matters totaled $700 million as of September 30, 2026.
  • Separately, RCA became registered owner of Praxair Rus LLC in July 2026 through enforcement of a Russian judgment.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Linde plc published the original content used to generate this news brief on October 30, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk