TeraWulf expands Kentucky Power contract, doubles Muskie campus capacity to 1 GW

By Public Technologies
  • Terawulf executed an amended electric service agreement with Kentucky Power, raising contracted capacity at its Muskie Data Campus to 1 GW.
  • Second 500 MW phase delivery moved up to 2029 from 2030, subject to Kentucky Public Service Commission sign-off.
  • Initial 500 MW phase remains slated to start ramping in 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Terawulf Inc. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202610050815PRIMZONEFULLFEED9839327) on October 05, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk