SSE brings first new turbine online in £80 million Lochay hydro upgrade

By Public Technologies
  • SSE returned the first new turbine generating unit to commercial operation under its £80 million refurbishment of Lochay Power Station in Perthshire.
  • The refurbishment will extend the 45MW station's operating life by at least 40 years, improving efficiency and output.
  • Unit 1 resumed generation in late September following its April 2025 shutdown; both units will be available for commercial operation over winter.
  • The station will shut in spring 2027 for Unit 2 refurbishment, including installation of the second new turbine generating unit.
  • Completion is expected in 2028, supporting modernization of the hydro fleet to maximize renewable generation from existing assets.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. SSE plc published the original content used to generate this news brief on November 06, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk