SEGRO Says Power Constraints Limit UK Data Centre Investment

By Public Technologies
  • SEGRO warned in an October 20, 2026 analysis that power constraints threaten UK data center investment despite strong demand and available capital.
  • Ofgem’s proposed milestones for data centers above 10MW risk penalizing credible, phased developments by requiring customer commitments before power availability is certain.
  • A proposed 2.5% commitment fee would require £23.8 million for a 100MW project, creating significant financial exposure for developers.
  • The analysis urged capped exposure, progressive security releases and a dedicated pathway for phased data center campuses.
  • Network operators should face binding delivery obligations, with developers able to challenge repeated connection delays rather than commit capital without recourse.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. SEGRO plc published the original content used to generate this news brief on October 20, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk