Paragon, HBF research finds only 50.8% of planning condition applications decided on time

By Public Technologies
  • Paragon Bank and Home Builders Federation research found only 50.8% of planning condition applications determined within eight weeks, threatening housing delivery.
  • On-time determinations fell from 55.6% in 2023/4 to 51.8% in 2024/5.
  • Median determination time reached 70 days in 2025/26, exceeding the statutory target by 25%.
  • Delays tie up SME builders' capital, increase financing costs and threaten development viability, potentially postponing new housing projects.
  • Planning departments face staffing shortages, with 90% below full capacity; HBF urged adequate resourcing and national performance monitoring.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Paragon Banking Group plc published the original content used to generate this news brief on October 26, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk