Miso Selects Consortium Of Ameren, Gridliance, Dairyland To Deliver Foundational Energy Grid Project In Iowa

By Reuters News

- Ameren Corporation AEE.N:

  • MISO SELECTS CONSORTIUM OF AMEREN, GRIDLIANCE, DAIRYLAND TO DELIVER FOUNDATIONAL ENERGY GRID PROJECT IN IOWA

  • AMEREN CORPORATION - MISO ESTIMATES COST OF IOWA TRANSMISSION PROJECT AT $1.23 BILLION

  • AMEREN CORPORATION - ATXI, GRIDLIANCE, DAIRYLAND TO OWN 42.5%, 42.5%, 15% OF PROJECT

  • AMEREN CORPORATION - 765-KV SCOPE OF PROJECT EXPECTED IN SERVICE JUNE 1, 2034; 345-KV SCOPE JUNE 1, 2032

Further company coverage: AEE.N

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk