Kumba Iron Ore's Sishen UHDMS project reaches 60% completion

By Public Technologies
  • Kumba Iron Ore’s R 11.2 billion Sishen UHDMS project remains on track for its main tie-in completion before end-2026.
  • Overall project progress reached about 60%, with construction roughly 50% complete.
  • Project capital spending remains within guidance of R 3 billion to R 3.2 billion for the year.
  • Final module conversion is scheduled for 2028, increasing premium-grade output, reducing waste mining and extending Sishen’s mine life.
  • A separate 63 MW solar project at Sishen remains on track for completion in 2028 under an offtake agreement with Envusa.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Kumba Iron Ore Ltd. published the original content used to generate this news brief via SENS, the regulatory disclosure system operated by the Johannesburg Securities Exchange (JSE) (Ref. ID: S605207), on October 20, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk