Kentucky Power, TeraWulf expand Muskie Data power deal, targets $100 million in customer bill credits

By Public Technologies
  • AEP unit Kentucky Power finalized an amended contract to double TeraWulf’s contracted demand at the Muskie Data campus to 1 GW.
  • Deal targets USD 100 million of winter bill credits for Kentucky Power residential customers over 10 years, starting in 2029.
  • Second 500-MW phase delivery pulled forward to 2029 from 2030, subject to Kentucky regulator sign-off.
  • TeraWulf to cover estimated financing costs tied to Kentucky Power’s planned 760-MW combined-cycle plant at Big Sandy.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. AEP - American Electric Power Company Inc. published the original content used to generate this news brief via PR Newswire (Ref. ID: CL63375) on October 05, 2026, and is solely responsible for the information contained therein.

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk