- First Quantum Minerals' FM.TO expanded Kansanshi copper mine in Zambia is on track to process about 27 million metric tons of ore in 2026, exceeding its design capacity by 8% and supporting a stronger production outlook, the company said on Wednesday.


Here are some details:

  • Kansanshi Mining's $1.2 billion S3 expansion project was commissioned in August 2025 and is expected to double the mine's copper output to about 277,000 metric tons annually

  • A new 25-million-ton-a-year sulphide processing line is at the centre of the expansion, more than doubling Kansanshi's processing capacity

  • The company said strong availability, utilisation and milling performance helped the plant exceed its throughput target

  • The increased capacity has enabled Kansanshi to process substantial quantities of lower-grade sulphide ore, the company added

  • Zambia has become First Quantum's main copper-producing jurisdiction, contributing about 93% of group output in 2025 after the suspension of Cobre Panama in 2023

  • The Kansanshi expansion is a key part of Africa's No. 2 copper producer Zambia's target to lift annual output to 3 million tons by 2031 from 890,346 tons last year

  • Demand for copper is being driven by the global transition to cleaner energy


Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk