Exxon starts Uaru oil production, lifting Guyana's capacity to 1.1 million bpd

By Reuters News

- ExxonMobil XOM.N said on Monday it had started production at its Uaru project in Guyana's offshore Stabroek block, bringing the South American country's installed oil production capacity to 1.1 million barrels per day.

Uaru is the fifth ExxonMobil-led development project to start production in the Stabroek block. The company is bringing projects using floating production, storage and offloading, or FPSO, vessels online in stages to expand Guyana's output capacity.

Here are more details:

  • The Errea Wittu FPSO vessel has an initial production capacity of 250,000 barrels per day

  • ExxonMobil said the vessel is expected to achieve its initial capacity in the first quarter of 2027

  • Errea Wittu has storage capacity of 2 million barrels and joins the Destiny, Unity, Prosperity and One Guyana FPSOs

  • Last week, the US energy major approved funding for the Longtail project, its eighth planned Stabroek development

  • ExxonMobil Guyana operates the Stabroek block with a 45% interest, while Chevron CVX.N holds 30% through its 2025 acquisition of Hess, including Hess' Guyana assets

  • CNOOC Petroleum Guyana holds the remaining 25% interest in the Stabroek block

Capital Com is an execution-only service provider. The present material must be regarded as marketing communication and should not be interpreted as investment research or investment advice. Any opinion that may be provided on this page does not constitute a recommendation by Capital Com or its agents. We do not make any representations or warranty on the accuracy or completeness of the information that is provided on this page. If you rely on the information on this page, then you do so entirely at your own risk