Bahrain retenders 100MW solar project after receiving bids from Acwa, Yellow Door Energy

By Zawya

By Anoop Menon

Bahrain’s Electricity and Water Authority (EWA) has relaunched the tender for its 100-megawatt (MWac) Bilaj Al Jazayer solar power project, nearly five months after receiving bids from Saudi-listed ACWA and UAE-based Yellow Door Energy.

The authority has set 20 December 2026, as the deadline for submitting bids under the new international tender, according to a notice published on Bahrain’s tender portal.

The project, which will be developed under a build-own-operate (BOO) model, is now scheduled to begin commercial operations on December 31, 2028, compared with an earlier target of the third quarter of 2027.

EWA has not disclosed the reason for retendering the project or the status of the bids received under the previous procurement process.

The authority originally issued the request for proposals (RFP) on 16 October 2025, with an initial bid submission deadline of 28 December 2025.

A contract award had been expected in the second quarter of 2026, according to a Zawya Projects report.

However, bids were opened only in June 2026, with Yellow Door Energy Projects Co., the Bahrain subsidiary of UAE-based Yellow Door Energy, and Saudi-listed ACWA emerging as the two bidders.

According to the June bid-opening results, Yellow Door Energy submitted a price of 11.398 Bahraini fils per kilowatt-hour, equivalent to approximately 3.02 US cents/kWh, compared with Acwa's 15.440 fils/kWh, or approximately 4.10 US cents/kWh. The tariff interpretation was based on the published bid figures and was not explicitly confirmed in the tender notice.

Under the relaunched tender, the successful developer will be responsible for financing, designing, constructing, operating and maintaining the photovoltaic facility over a 25-year period, including eventual decommissioning and site restoration.

The scope covers the solar generation facilities and associated infrastructure, including access and internal roads.

EWA said the project will be procured through a single-stage RFP process, with bidders initially assessed against minimum financial and technical eligibility requirements before proceeding to detailed technical and financial evaluation.

The project forms part of Bahrain's efforts to increase renewable energy's share of its power generation mix to 20 percent by 2035.

(Writing by Anoop Menon; Editing by Dennis Daniel)

(anoop.menon@lseg.com)

Subscribe to our Projects' PULSE newsletter that brings you trustworthy news, updates and insights on project activities, developments, and partnerships across sectors in the Middle East and Africa.

Capital.com is an execution-only brokerage platform and the content provided on the Capital.com website is intended for informational purposes only and should not be regarded as an offer to sell or a solicitation of an offer to buy the products or securities to which it applies. No representation or warranty is given as to the accuracy or completeness of the information provided.

The information provided does not constitute investment advice nor take into account the individual financial circumstances or objectives of any investor. Any information that may be provided relating to past performance is not a reliable indicator of future results or performance.

To the extent permitted by law, in no event shall Capital.com (or any affiliate or employee) have any liability for any loss arising from the use of the information provided. Any person acting on the information does so entirely at their own risk.

Any information which could be construed as “investment research” has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such is considered to be a marketing communication.