Artemis Gold Expects 2026 AISC at High End of USD 925-1,025 per Ounce Guidance
- Artemis Gold remains on track for 2026 gold production of 265,000–290,000 ounces.
- All-in sustaining costs are expected at the high end of US$ 925–1,025 per ounce, reflecting higher reagent, contractor and diesel costs.
- Year-to-date production reached 205,532 ounces, with all-in sustaining costs of US$ 1,024 per ounce.
- Growth capital spending is forecast at $685 million–$755 million, with Phase 1A and EP2 spending weighted toward year-end.
- Phase 1A commissioning remains scheduled for December 2026; EP2 is on track for the second half of 2028.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Artemis Gold Inc. published the original content used to generate this news brief on November 04, 2026, and is solely responsible for the information contained therein.