Serabi Gold Presents Coringa Production Growth Plans
- Serabi Gold expects Coringa to reach full ramp-up by end-2026, with consolidated production currently capped near 45,000 ounces by permitting restrictions.
- An operating permit expected in the first half of 2027 would remove Coringa's processing restrictions.
- The resource target is 1,700,000–2,000,000 ounces, up from 1,400,000 ounces; updated estimates are expected in the second quarter of 2027.
- A fourth ball mill installed in the fourth quarter of 2026 increases plant throughput capacity to 900 metric tons per day.
- Cash totaled US$ 63.2 million at September 30, 2026, with no debt.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Serabi Gold plc published the original content used to generate this news brief on November 16, 2026, and is solely responsible for the information contained therein.