- Exelon unit ComEd secured Illinois Commerce Commission approval for its GRIT transmission project in Cook and DuPage counties.
- The project includes four underground 138kV transmission lines and one new substation to improve grid reliability.
- A transmission ring connecting three substations will provide alternative power routes to support growing customer demand.
- Substation construction begins this fall; underground transmission work starts in January of next year.
- The project is scheduled to enter service in the second quarter of 2029.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Exelon Corporation published the original content used to generate this news brief via Business Wire (Ref. ID: 20261022573071) on October 22, 2026, and is solely responsible for the information contained therein.