Redeia says Spain-Ceuta power interconnection enters service, enabling instant backup supply

By Public Technologies
  • Redeia reported the mainland Spain–Ceuta power interconnection is fully energized and in service, providing instant backup for Ceuta’s demand.
  • Transmission grid works run by Red Eléctrica finished in December 2025; the first circuit was energized on March 13, 2026.
  • Distribution facilities were first energized on June 30, 2026; synchronization tests were completed on July 22.
  • The permanent connection was completed on Aug. 10, enabling supply support from the Iberian and broader European system.
  • Commercial electricity exchange scheduling is set to start on Nov. 1 under a decree published on June 30, 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Redeia Corporación SA published the original content used to generate this news brief on September 21, 2026, and is solely responsible for the information contained therein.

Capital.com is an execution-only brokerage platform and the content provided on the Capital.com website is intended for informational purposes only and should not be regarded as an offer to sell or a solicitation of an offer to buy the products or securities to which it applies. No representation or warranty is given as to the accuracy or completeness of the information provided.

The information provided does not constitute investment advice nor take into account the individual financial circumstances or objectives of any investor. Any information that may be provided relating to past performance is not a reliable indicator of future results or performance.

To the extent permitted by law, in no event shall Capital.com (or any affiliate or employee) have any liability for any loss arising from the use of the information provided. Any person acting on the information does so entirely at their own risk.

Any information which could be construed as “investment research” has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such is considered to be a marketing communication.