Redeia completes Abanto substation expansion in Bizkaia
- Redeia subsidiary Red Eléctrica completed the expansion of its 400 kV Abanto substation in Bizkaia to strengthen electricity supply.
- The expansion adds two connection bays serving local businesses and municipalities, including a large industrial consumer.
- Investment totaled nearly EUR 3 million. The project is eligible for EU NextGenerationEU funding under Spain’s recovery plan.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Redeia Corporación SA published the original content used to generate this news brief on November 12, 2026, and is solely responsible for the information contained therein.