Centaurus Metals presents Jaguar nickel project funding progress ahead of investment decision
- Centaurus Metals outlined progress toward financing its fully permitted Jaguar nickel project in Brazil at the Australia Metals & Mining Conference.
- Funding package targeted for completion in Q4 2026 to support a final investment decision; senior debt facility well advanced.
- Glencore and CNGR secured offtake covering 100% of production for the first five years, each committing US$ 20 million in strategic equity.
- Five-year offtake contracts commence in H1 2029, covering at least 60,000 metric tons of nickel concentrate annually.
- Jaguar's initial 15-year open-pit plan targets average annual nickel production of 18,700 metric tons.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Centaurus Metals Limited published the original content used to generate this news brief on November 11, 2026, and is solely responsible for the information contained therein.